Governor Gavin Newsom signed AB 1577 on September 21, 2026, chaptered as Cal. Stats. 2026, ch. 434 and adding Public Resources Code section 25302.10. From January 1, 2027, owners and operators of data centers of at least 10 megawatts must report operational data to the Energy Commission upon energization and after any substantive change. The Commission publishes the data annually in anonymized, aggregated form and adds biennial data-center load assessments to integrated energy policy reports from 2029.
Enrolled text (California Legislative Information) →
Key points
- AB 1577 was signed September 21, 2026, chaptered as Cal. Stats. 2026, ch. 434; it takes effect January 1, 2027.California Legislative Information
- It covers data centers with at least 10 megawatts of electrical capacity.California Legislative Information
- Owners and operators report at energization and after substantive changes: load, PUE, refrigerants, onsite generation and storage.California Legislative Information
- The Commission publishes submitted data in anonymized, aggregated form.California Legislative Information
- Biennial data-center load assessments join integrated energy policy reports starting in 2029.California Legislative Information
- Publicly funded research, public safety, national security, and publicly owned facilities are excluded.California Legislative Information