California enacted AB 2469 (Chapter 436, Statutes of 2026), adding Government Code section 65964.7, on September 21, 2026. Cities and counties may not approve permits for data-center construction, or expansions that increase peak water use, unless applicants provide a water supply assessment, projected water use and efficiency measures, workforce disclosures and, from January 1, 2028, a water scarcity plan covering five drought categories. Applicants must bear the full cost of required water infrastructure. The act takes effect January 1, 2027.
Enrolled text (California Legislative Information) →
Key points
- Cities and counties may not approve data-center construction or expansions increasing peak water use without the required submissionsCalifornia Legislative Information
- Applicants must provide a water supply assessment, projected water use, and water efficiency measuresCalifornia Legislative Information
- Beginning January 1, 2028, applicants must submit a water scarcity plan covering five drought categories defined by the U.S. Drought MonitorCalifornia Legislative Information
- Applicants must disclose workforce composition, job classifications, employment duration, wages, and benefitsCalifornia Legislative Information
- Applicants bear the full cost of required water conveyance, treatment, storage, or distribution infrastructure improvementsCalifornia Legislative Information